Project Illustrations

What to expect

At DAVS, we want to ensure you are clear on our project processes and understand our timeline for AV integration, so we’re on the same page when it comes to your new system.

Of course, the more complex the project, the longer it will take. If your project requires new construction or remodelling, we’ll work with your contractors to minimise delays. Additionally, because audio visual equipment is very sensitive and requires a clean room, we ask that before we get started your carpet is down, walls are painted and the area is dust-free before installation begins.

Our Project Illustration timeline will give you a general idea of our basic steps and the typical timing of our activities, helping to set realistic expectations for your upcoming project.

Sample Timeline: Medium-size project over 9 weeks

Weeks 1-3

  • Discovery Session & Conditions of Satisfaction
  • Preliminary Project Scope and Budget Development
  • Deliver Final Scope and Proposal
  • Complete Credit Application
  • Issue PO or Contract Signed

Weeks 4-5

  • Order Equipment
  • Schedule Installation

Week 6

  • Complete Infrastructure Drawings

Week 7

  • Complete CAD/Programming

Week 8

  • Onsite Installation

Week 9

  • System Training and Sign-Off